Guernsey Water wastewater project requires Rue de la Bouillerie closure from 24 June to 2 September 2013

June 23rd, 2013 by Guernsey Water

Guernsey Water would like to remind islanders that the next phase of its wastewater network extension programme will be commencing in the Les Naftiaux area of St Andrew from Monday 24 June 2013.

While the project to extend the main sewer will take approximately 10 months to complete, contractors will be working in one road at a time, and every effort will be made to minimise inconvenience to residents and businesses where possible.

The programme of road closures is as follows:

24 June to 2 September 2013

Rue de la Bouillerie (incorporating Les Naftiaux Estate)

Rue de La Bouillerie leading to St Andrew's Primary School (click image to expand - ©RLLord)

Rue de La Boullerie leading to St Andrew’s Primary School (click image to expand – ©RLLord)

3 September to 25 November 2013

Rue des Bailleuls

26 November 2013 to 3 February 2014

Rue des Landes/Rue des Naftiaux

4 February 2014 to 17 March 2014

St Andrews Road (from Les Poidevins junction to Rue de la Bouillerie junction)

18 March 2014 to 30 April 2014

Rue Marquand

More information on the traffic management arrangements for the area can be obtained from the Environment Department Road Works website.

 